Tom
@Tallish_Tom@mastodon.scot  ·  activity timestamp 7 days ago

Interesting real world data, on 1GW firm power supply.

Masdar UAE - solar + batteries.
Cost USD 6 billion.
Construction time 2 years (caveat, not sure if this is a tranche or all of it)

Hualong One
Cost USD 3 billion (from actuals)
construction time 5 years

So purely on construction cost, large scale firm solar is twice the price of Chinese nuclear.

Note, fuel, op costs, water needs, llife time, site cleanup etc not accounted for.

#nuclear #solar #batteries #energytransition

  • Copy link
  • Flag this post
  • Block
Tom
@Tallish_Tom@mastodon.scot replied  ·  activity timestamp 7 days ago

Of course European and USA data puts the nuclear cost equivalent at 10x that of Hualong One and the construction time at 2-3x. 🤦🏻‍♂️

OTOH it is not as sunny, and seasonal variation is bigger in Europe than the UAE.

OTOOH firmed solar is on track to halve in price over the next 10-15 years (conservatively) so, there's that too.

  • Copy link
  • Flag this comment
  • Block
Log in

bonfire.cafe

A space for Bonfire maintainers and contributors to communicate

bonfire.cafe: About · Code of conduct · Privacy · Users · Instances
Bonfire social · 1.0.0 no JS en
Automatic federation enabled
  • Explore
  • About
  • Members
  • Code of Conduct
Home
Login